Foundation reinforcement for structural beam. And hardware installation for structural engenieer design.
Full structural framing fixing for smoke and fire / framing inspection
Full framing nail clean up
Framing fix for kitchen and bathroom wall to the original frame. Two windows rebuild.
Insulation for all exterior walls as required by structural inspection. R13 for walls labor and material.
New window trim custom made in wood 2 x 4
Willy 5 days = $1500
David 5 days = $1000
Ramon 5 days = $1250
Taira 5 days = $750
Fernando 5 days = $1000 Material = $1000 Router Bits = 3@45 = $135 Dado Disc = $300 Paint and primer = $200 Total ammount $7135
Aditional cost of drywall material for raise in material cost.